Petaluma Bridge - Emergency Bridge Fender Repair - Project Complete

June 3rd, 2024


Work has completed on the MRN37 PM: 14.47 Emergency Bridge Fender Repair Project. The project temporarily repaired the Petaluma River Bridge fender following a water vessel allision. The work entailed positioning a crane mounted on a spud barge just outside the navigation channel, removing the damaged fenders from the channel, and installing a floating pneumatic sling fender system consisting of two floating pneumatic sling fenders to protect the bridge structure.